If an activity is not on the critical path,then the project cannot be delayed if that activity is delayed
Correct Answer:
Verified
Q18: The project network diagram describes sequential relationships
Q19: The path in a project network with
Q20: The values assigned to the nodes in
Q21: The slack of an activity is the
Q21: The earliest finish time for an activity
Q23: Activities that are not on the critical
Q25: The PERT three-estimate approach can be used
Q26: When making a backward pass through a
Q27: Only activities on the critical path are
Q27: Crashing cannot be accomplished by using different