Consider the following PERT/CPM network with estimated times in weeks.The project is scheduled to begin on May 1. The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity:
a.Give the expected project completion date and the critical path.
b.By what date are you 99% sure the project will be completed?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q1: Crashing refers to an unanticipated delay in
Q2: The variance in the project completion time
Q6: When activity times are uncertain, total project
Q8: The earliest finish time for the final
Q12: All activities on a critical path have
Q12: The earliest start time for an activity
Q19: A critical activity can be part of
Q20: The length of time an activity can
Q31: A project consists of five activities.Naturally the
Q32: Consider a project that has been modeled
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents