Timing of Revenue Recognition/percentage of Completion

Question 88

Essay

Timing of revenue recognition/percentage of completion
Crush Inc. provides demolition services. In order to determine the progression of its projects, the company could use several measures, including estimated labour hours, total machine hours, and output of material demolished. A project Crush currently has underway has taken 400 labour hours, 900 machine hours, and 2,000 tons of material output. The estimated total resources required (and resulting outputs) for this project are 1,000 labour hours, 1,400 machine hours and 4,500 tons of materials.
Instructions
Consider the three alternative means of tracking percentage completion. Under each method, calculate the percentage-completion rate for this project.

Correct Answer:

verifed

Verified

a) Labour Hours
400 hours / 1,...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents