Given the Earliest and Latest Finish Times for Each of These

Question 51

Essay

Given the earliest and latest finish times for each of these activities, what are the activity lengths?
 Activity  EF  LF  Predecessors  A 33 B 1010 A  C 513 A  D 1818 B  E 1518 B  F 1119 C  G 819 C  H 2323 D, E  I 1523 F, G  J 2424 H, I \begin{array} { | c | c | c | c | } \hline \text { Activity } & \text { EF } & \text { LF } & \text { Predecessors } \\\hline \text { A } & 3 & 3 & \cdots \\\hline \text { B } & 10 & 10 & \text { A } \\\hline \text { C } & 5 & 13 & \text { A } \\\hline \text { D } & 18 & 18 & \text { B } \\\hline \text { E } & 15 & 18 & \text { B } \\\hline \text { F } & 11 & 19 & \text { C } \\\hline \text { G } & 8 & 19 & \text { C } \\\hline \text { H } & 23 & 23 & \text { D, E } \\\hline \text { I } & 15 & 23 & \text { F, G } \\\hline \text { J } & 24 & 24 & \text { H, I } \\\hline\end{array}

Correct Answer:

verifed

Verified

\[\begin{array} { | c | c | }
\hline \t...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents