Consider the System Composed of Four Processes Linked by a Conveyor

Question 59

Multiple Choice

Consider the system composed of four processes linked by a conveyor belt. There is no storage between these processes pictured below and market demand of 40 units per hour drives the conveyor belt. Assume that no defective units are made. Which statement is best? Consider the system composed of four processes linked by a conveyor belt. There is no storage between these processes pictured below and market demand of 40 units per hour drives the conveyor belt. Assume that no defective units are made. Which statement is best?   A) The average time a unit spends in Process 1 is 2 and a half minutes. B) The average time a unit spends in Process 2 is 5 minutes. C) The flow time for a unit through the entire process is 33 minutes. D) The flow rate through the entire process is 160 units per hour.


A) The average time a unit spends in Process 1 is 2 and a half minutes.
B) The average time a unit spends in Process 2 is 5 minutes.
C) The flow time for a unit through the entire process is 33 minutes.
D) The flow rate through the entire process is 160 units per hour.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents