If the net present value of a project is zero,based on a discount rate of 16%,which of the following statements about the project's internal rate of return is correct?
A) It is equal to 16%.
B) It is less than 16%.
C) It is greater than 16%.
D) It cannot be determined from the information given.
Correct Answer:
Verified