Question 80

Multiple Choice

Which of the following statements is incorrect?


A) It is possible to compute multiple IRRs for a single project.
B) A problem with IRR is that it does not adjust for the scale of the project.
C) A NPV profile plots the relationship between the riskiness of a project and the associated NPVs.
D) The NPV and IRR always provide the same rankings for a set of possible projects.
E) IRR provides information in a form that is useful to managers.