Early in 2012, Forest Ltd. signed a contract to construct a warehouse. Forest's management estimated the gross profit on the contract to be $740,000, as indicated by the following: At the end of 2012, the status of the work on the contract was as follows:
How much revenue can be recognized on this contract for 2012, assuming that Forest uses the
Percentage of completion basis for long-term construction contracts (round to nearest dollar) ?
A) $333,000
B) $863,333
C) $1,575,000
D) $1,711,957
Correct Answer:
Verified
Q64: Soorya Manufacturing makes educational toys that are
Q65: Pool Contractors (PC)entered into a contract to
Q66: Lagory Co. started a contract in June
Q68: Algae builds large ships and uses the
Q69: How is revenue recognized on a cost
Q70: Soorya Manufacturing makes educational toys that are
Q71: Tyco Ltd entered into a contract to
Q73: Which statement about the percentage of completion
Q73: Nova Construction Company (NCC)entered into a contract
Q74: Jones Contractors Inc. agreed to construct a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents