A project consists of five activities.Naturally the paint mixing precedes the painting activities.Also,both ceiling painting and floor sanding must be done prior to floor buffing.
a.Construct the PERT/CPM network for this problem.
b.What is the expected completion time of this project?
c.What is the probability that the project can be completed within 9 hr.?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q9: When activity times are uncertain,an activity's most
Q15: It is possible to have more than
Q18: Precedence relationships among activities is critical in
Q24: Why should projects be monitored after the
Q28: Explain how and why all predecessor activities
Q42: Use the following network of related
Q44: Suppose that,after analyzing a PERT/CPM ntwork,the project
Q45: For the project represented below,determine the
Q46: A project network is shown below.Use a
Q48: Use the following network of related
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents