The goal of ____ is to know the status of the schedule,influence the factors that cause schedule changes,determine that the schedule has changed,and manage changes when they occur.
A) activity duration estimating
B) schedule development
C) schedule control
D) activity resource estimating
Correct Answer:
Verified
Q61: _ have no duration and no resources
Q68: Critical chain scheduling protects tasks on the
Q74: Project managers must use discipline to control
Q76: Outputs of _ include activity duration estimates
Q77: Project managers often illustrate progress with a
Q78: A(n)_ is a schematic display of the
Q80: _ is the one variable in project
Q81: Many project management software programs come with
Q82: What are the basic reasons for creating
Q93: A(n) _ Gantt chart compares planned and