____ is the amount of time an activity can be delayed without delaying the early start date of any immediately following activities.
A) Total slack
B) Total float
C) Free time
D) Free slack
Correct Answer:
Verified
Q41: In a _ relationship,the "from" activity must
Q42: _ occur when two or more activities
Q43: In a _ relationship,the "from" activity cannot
Q44: _ results in supporting detail to document
Q45: _ dependencies are inherent in the nature
Q47: _ provide(s)a standard format for displaying project
Q48: The _ is a network diagramming technique
Q49: In a _ relationship,one task cannot finish
Q50: A _ is a hierarchical structure that
Q51: On a network diagram,all arrowheads should face