Solved

Which of the Following Statements Is NOT True About the PERT

Question 15

Multiple Choice

Which of the following statements is NOT true about the PERT method of project scheduling?


A) PERT requires three time estimates for scheduling a given activity.
B) PERT assumes that the actual activity times are distributed according to the beta probability distribution.
C) PERT assumes that the statistical variation in total project completion times can be computed by multiplying variances along the critical path.
D) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents