Below are the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the costs include both direct and indirect costs.
What are the total time of this project and total normal cost?
A) Total time is 13 days,total cost is $1,200
B) Total time is 12 days,total cost is $1,700
C) Total time is 11 days,total cost is $1,600
D) Total time is 10 days,total cost is $1,750
E) Total time is 9 days,total cost is $1,700
Correct Answer:
Verified
Q69: You have just computed a Z=2.55 in
Q70: A listing of immediate predecessor activities is
Q71: A company wants to use CPM analysis
Q72: A simple project listing of five
Q73: You ask your subordinates how long it
Q75: You are working on a project that
Q76: You have determined the critical path in
Q77: If you have an optimistic time of
Q78: For an activity in a Single Time
Q79: A company must perform a maintenance
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents