Solved

Consider the Following Work Breakdown Structure What Is the Estimated Standard Deviation in the Time for

Question 82

Multiple Choice

Consider the following work breakdown structure:  Start  Finish  Duration (Days)   Activity  Node  Node  Optimistic  Most Likely  Pessimistic  A 12415059 B 13546066 C 24587082 D 34324144\begin{array}{cccccc}&\text { Start }&\text { Finish }&&\text { Duration (Days) } \\\text { Activity } & \text { Node } & \text { Node } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { A } & 1 & 2 & 41 & 50 & 59 \\\text { B } & 1 & 3 & 54 & 60 & 66 \\\text { C } & 2 & 4 & 58 & 70 & 82 \\\text { D } & 3 & 4 & 32 & 41 & 44\end{array} What is the estimated standard deviation in the time for activity D?


A) 0 days
B) 2 days
C) 3 days
D) 4 days
E) 12 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents