Consider a three sequentially stepped process named as Process A, Process B and Process C.Input comes into Process A.Output form A goes into Process B.Output from B goes into Process C.Output of C is the final output.Suppose that it takes 2 minutes per unit in Process A, 3 minutes per unit in Process B and 1 minute per unit in Process C.What will be maximum steady state output from this system?
A) 30 per hour
B) 60 per hour
C) 20 per hour
D) 10 per hour
E) cannot tell since it depends on the input rate.
Correct Answer:
Verified
Q41: A process flowchart uses which of the
Q44: According to Little's law, which of the
Q44: Consider a business that can be run
Q45: Consider a three sequentially stepped process named
Q46: To reduce process throughput time, you might
Q48: The long-term relationship among the inventory, throughput,
Q49: Which of the following terms describes the
Q50: To reduce process flow time, you might
Q52: Which of the following production process terms
Q53: Consider a three sequentially stepped process named
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents