Starting with a due date and scheduling a job through work centers so that the job finishes at each work center just in time for the next center is called
A) forward scheduling.
B) backward scheduling.
C) theory of constraints scheduling.
D) batch scheduling.
Correct Answer:
Verified
Q17: For services,the most common priority dispatch rule
Q18: A bottleneck is
A) a resource that has
Q19: Lead time for completion of a job
Q20: The theory of constraints (TOC)is
A) a strategic
Q21: First come,first served is widely used in
Q23: A bottleneck should never be blocked or
Q24: A manufacturer of water filtration pumps is
Q25: If the critical ratio of a job
Q26: Which of the following statements about batch
Q27: Which of the following is a tactic