If a project path has an expected duration of 10 days and a standard deviation of 3 days, what is the probability that the path will be completed in 13 days or less?
A) 50 percent
B) 33 percent
C) 75 percent
D) 84 percent
Correct Answer:
Verified
Q23: Task X has a 82% probability of
Q24: Given the project plan shown below, which
Q25: For a project with many task paths
Q25: Task X has a most likely duration
Q26: Given the tasks, estimated durations, and crash
Q29: Given the project plan shown below, for
Q30: Given the tasks, estimated durations, and crash
Q31: Given the tasks, estimated durations, and crash
Q32: Task X has a most likely duration
Q32: The four tasks below must be completed
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents