Tony has realized that two activities in his project cannot be done at the same time because not enough resources are available.Activity 3 is critical and has a duration of 5 days.Activity 4 has 2 days of slack and a duration of 2 days.How will he decide which activity should be scheduled first?
A) The activity with the smallest duration
B) The activity with the least slack
C) The activity with the most slack
D) The activity with the lowest identification number
E) The activity with the highest cost
Correct Answer:
Verified
Q30: These are all guidelines a project manager
Q31: In a resource-constrained project the second priority
Q32: All of the following are benefits of
Q33: When deciding which staff to team-up to
Q35: Having one person responsible for performing several
Q37: This is used to compare the cost
Q38: A(n)_ constraint addresses the sequence in which
Q39: In a resource-constrained project the third priority
Q44: Why is it necessary to have a
Q52: Which of the following is NOT one
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents