When a Project Manager Must Reduce Project Duration but Resources

Question 25

Multiple Choice

When a project manager must reduce project duration but resources are constrained, creating a software program that will have fewer features than originally planned or building a house without the bonus room the owner originally specified in the plans would both be examples of


A) Fast-tracking.
B) Using critical-chain project management.
C) Reducing project scope.
D) Compromising quality.
E) Doing it twice-first fast and then correctly.

Correct Answer: