An audit team designed a sample that would provide a 10 percent risk of overreliance that not more than 7 percent of sales invoices lacked credit approval.From previous audits,the audit team expected that 3 percent of the sample invoices lacked proper approval.From the sample of 90 invoices,7 were found to lack credit approval.Using AICPA sample evaluation tables,the upper limit rate of deviation was
A) 3.3%.
B) 4.5%.
C) 7.8%.
D) 12.8%.
Correct Answer:
Verified
Q87: Which of the following steps in the
Q88: Taylor LaRussa,an audit manager,considered the control risk
Q89: In which step of a sampling plan
Q90: The interpretation of the upper limit rate
Q91: Using AICPA sample evaluation tables,what is the
Q93: If the sample evidence does not support
Q94: If the _ exceeds the _,the audit
Q95: A type of sampling application in which
Q96: Which of the following best describes the
Q97: Which of the following would not be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents