Which of the following is not one of the recommended guidelines for developing useful work package estimates?
A) Estimates should be made by those responsible for the work
B) Use several people to estimate the same work
C) Estimates should be based on normal conditions
D) Estimates should include a normal level of contingency
E) Estimates should be independent of other projects
Correct Answer:
Verified
Q22: Typical kinds of costs found in a
Q23: The accuracy of bottom-up estimates will typically
Q24: Estimates that are usually derived from analogy
Q25: In a learning curve, the improvement ratio
Q26: The _ factor in estimating project times
Q28: The tendency to over-estimate project time and
Q29: A manager getting further into a project
Q30: Which of the following would be considered
Q31: The estimating factor known as _ considers
Q32: Resource shortages, in the form of people,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents