Consider the portion of a project depicted by this graph: What is the earliest finish time for activity 10-11 (far right hand side) , if the earliest start time of 8-10 (upper left hand side) is 12, and the earliest start time of 9-10 (lower left hand side) is 13?
A) 22
B) 23
C) 24
D) 25
E) 26
Correct Answer:
Verified
Q45: Concerning PERT and CPM:
A)These are two different
Q46: To _ an activity means to shorten
Q46: Which of the following is determined as
Q47: Project management differs from management of more
Q48: In a project network the critical path
Q51: Which of the following is not true
Q53: Activity 7-8 is directly preceded by two
Q54: Which of the following is not a
Q55: In PERT, the path with the fewest
Q57: Which of the following would probably not