Suppose that you can schedule a worker for up to 4 hours per day.The total benefit and total cost functions are B(H) = 1,300H - 20H2 and C(H) = 500H + 60H2.The corresponding formulas for marginal benefit and marginal cost are MB(H) = 1,300 - 40H and MC(H) = 500 + 120H.For how many hours should you schedule the worker?


A) 11.25 hours
B) 2.5 hours
C) 5 hours
D) 0 hours