The life cycle of a project includes which of the following phases?
I.Initiation
II.Planning and scheduling
III.Growth and maturity
IV.Closeout
A) I and II only
B) II and III only
C) I, II, and IV only
D) II, III, and IV only
E) I, II, III, and IV
Correct Answer:
Verified