Use the Earned Value Table to Determine the Schedule Performance
Question 41
Question 41
Multiple Choice
Use the earned value table to determine the schedule performance index given the indicated state of the project. Activity A B CDEFG Monthly Plan Monthly Act 585085090010350400750650151251,2751,4001,3502065028003,4503,875254,5006805,1804,780303504001253001,1758503587512002,0752,000 Plan 1,2005251,9257,6501,0801,0001,50014,880% Complete 100%100%100%95%75%80%45%
A) 0.89 B) 0.92 C) 1.09 D) 1.13