Use the data to calculate the schedule performance index for the project for the end of week 10.The earned value as of the end of week 10 is indicated in the table.All amounts are in thousands of dollars. Duration (weeks)
A) 1.24
B) 0.93
C) 0.81
D) 0.76
Correct Answer:
Verified
Q42: Duration (weeks) Q43: At the end of week 10,this Q44: The first step in earned value management Q45: The budget variance is calculated as: Q46: In earned value management,schedule variance is defined Q48: Use the data to calculate the Q49: In earned value management analysis,the cumulative amount Q50: The project baseline is established by combining Q51: Use the data to calculate the Q52: Use the earned value table to