Solved

Consider the Project That Is Neatly Summarized in This Table

Question 31

Multiple Choice

Consider the project that is neatly summarized in this table.What are the lowest priority activities when using the smallest amount of slack leveling heuristic?  Activity  Duration  Predecessors  Workers Required A23B4 A 4C6 A 2D7 B5E9C,D,E2\begin{array} { | l | l | l | l | } \hline \text { Activity } & \text { Duration } & \text { Predecessors } & \text { Workers Required } \\\hline \mathrm {A } & 2 & - & 3 \\\hline \mathrm { B} & 4 & \text { A } & 4 \\\hline \mathrm { C } & 6 & \text { A } & 2 \\\hline \mathrm { D } & 7 & \mathrm {~B} & 5 \\\hline \mathrm { E } & 9 & \mathrm { C } , \mathrm { D },\mathrm { E } & 2 \\\hline\end{array}


A) A and B
B) C and E
C) A and D
D) B and D

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents