A resource constraint can be exploited using CCPM methodology by:
A) Determining the priority among projects for access to the drum.
B) Scheduling each project to start based on the drum schedule.
C) Designating the critical chain as the chain from the first use of the constraining resource to the end of the project.
D) Resolving any conflicts if the creation of the capacity constraint buffers adversely affects the drum schedule.
Correct Answer:
Verified
Q76: A project is represented by the
Q77: The buffers supplied to non-critical paths in
Q78: A project is represented by the
Q79: A project is represented by the
Q80: Subcontractor deliveries are difficult to schedule with
Q82: A project that consists of six
Q83: An important element in critical chain scheduling
Q84: Drum buffers are:
A)A safety margin separating different
Q85: What are the implications for due dates
Q86: Use the project information in the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents