A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table.Use Goldratt's model to determine the aggregated buffer for this project.
A) 8.5 days
B) 15.9 days
C) 7.9 days
D) 15.5 days