A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table.Use Newbold's model to determine the aggregated buffer of one standard deviation for this project.
A) 31 days
B) 16 days
C) 8 days
D) 5 days
Correct Answer:
Verified
Q57: Your next project consists of 8 consecutive
Q58: The critical chain is usually the same
Q59: A project consists of four activities
Q60: Which statement about critical chain project management
Q61: A project is represented by the
Q63: A project consists of four consecutive
Q64: CCPM advocates performing all non-critical activities:
A)As late
Q65: A project is represented by the
Q66: A project consists of four consecutive
Q67: A project is represented by the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents