It took 44 hours of analysis to complete the first phase,but the second phase was done in 42 hours.If this learning rate continues,then the 8th analysis should take a mere:
A) 36 hours and 26 minutes,give or take.
B) 37 hours and 36 minutes,give or take.
C) 38 hours and 16 minutes,give or take.
D) 39 hours and 6 minutes,give or take.
Correct Answer:
Verified
Q20: The gentleman farmer and surrealist aficionado commissioned
Q21: Estimates based on the assumption that historical
Q22: The order of magnitude cost estimate is
Q23: When asked to provide an estimate of
Q24: What learning rate is being demonstrated if
Q26: Explain the difference between normal and expedited
Q27: A project manager is estimating costs on
Q28: Rank the four different types of cost
Q29: Effective comparative estimates rely most heavily on:
A)An
Q30: An order of magnitude estimate is usually
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents