To See If a Potential New Project Fits Within the Whole,an

Question 86

Multiple Choice

To see if a potential new project fits within the whole,an organization may consider interactions among various portfolio projects,such as interdependencies,competing resources,and timing.These activities best fit within the ________ step of the process phase of the portfolio selection process.


A) individual project analysis
B) screening
C) prescreening
D) portfolio selection

Correct Answer: