A project manager is using the internal rate of return method to make the final decision on which project to undertake.Which of these four projects has the highest internal rate of return?
A) $100,000 initial outlay with $10,000 cash inflows during the first two years,$20,000 during the third and fourth years,and $30,000 during the fifth year
B) $100,000 initial outlay with a $5,000 cash inflow during the first year,$15,000 cash inflow during the second year,and $25,000 cash inflows during years three through five
C) $75,000 initial outlay with a $5,000 cash inflow during the first year,increasing by $5,000 per year through the fifth year
D) $50,000 initial outlay with $5,000 cash inflows during the first two years,$15,000 during the third and fourth years,and $20,000 during the fifth year
Correct Answer:
Verified
Q51: Describe the use of a profile model
Q52: Net present value is being used to
Q53: A project manager is using the
Q54: The checklist model of project screening has
Q55: A project manager is using the
Q57: A project manager is using the
Q58: Your university is considering two projects to
Q59: How does a checklist project screening model
Q60: A company facing an interest rate of
Q61: Inatech is contemplating two different projects
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents