A Project Manager Is Using the Internal Rate of Return

Question 56

Multiple Choice

A project manager is using the internal rate of return method to make the final decision on which project to undertake.Which of these four projects has the highest internal rate of return?


A) $100,000 initial outlay with $10,000 cash inflows during the first two years,$20,000 during the third and fourth years,and $30,000 during the fifth year
B) $100,000 initial outlay with a $5,000 cash inflow during the first year,$15,000 cash inflow during the second year,and $25,000 cash inflows during years three through five
C) $75,000 initial outlay with a $5,000 cash inflow during the first year,increasing by $5,000 per year through the fifth year
D) $50,000 initial outlay with $5,000 cash inflows during the first two years,$15,000 during the third and fourth years,and $20,000 during the fifth year

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents