Solved

A Seven Activity Project Has the Activity Durations (In Weeks)and

Question 67

Essay

A seven activity project has the activity durations (in weeks)and costs shown in the table.It is possible to speed up every one of the activities by paying a little more; for example,activity A has a regular duration of 7 weeks and regular cost of $2000,but for $3000 activity A can be finished in 5 weeks and for $2500 activity A can be finished in 6 weeks.In addition to the activity costs shown in the table,there is an additional daily fixed cost of $450.What is the least expensive project completion cost?
A seven activity project has the activity durations (in weeks)and costs shown in the table.It is possible to speed up every one of the activities by paying a little more; for example,activity A has a regular duration of 7 weeks and regular cost of $2000,but for $3000 activity A can be finished in 5 weeks and for $2500 activity A can be finished in 6 weeks.In addition to the activity costs shown in the table,there is an additional daily fixed cost of $450.What is the least expensive project completion cost?

Correct Answer:

verifed

Verified

The normal completion cost is $18,000 fo...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents