Faced with significant schedule challenges,the project manager has an ethical responsibility to do all of the following EXCEPT:​ 


A)  willingly accept end dates dictated by customers or sponsors 
B)  persuade all stakeholders that the schedule makes sense 
C)  deliver the project according to the agreed-upon schedule 
D)  determine a schedule that is possible to achieve