All of the following statements correctly describe a contemporary approach to create the Work Breakdown Structure (WBS) for a project EXCEPT:
A) Project teams may adopt a top-down approach to construct the WBS.
B) Project teams may use a template or a WBS from a previous project as a starting point.
C) Project teams may rely upon the project manager to create all levels of the WBS.
D) Project teams may jump start the WBS construction with a brainstorming session.
Correct Answer:
Verified
Q16: The Work Breakdown Structure (WBS)is normally developed
Q17: A "top-down" approach to creating a WBS
Q18: By using a systematic process for creating
Q19: Plan scope management is the process of
Q20: Baselining is defined as a method of
Q22: Which of the following is NOT a
Q23: The method of dividing the project scope
Q24: The Work Breakdown Structure (WBS)is a framework
Q25: The project scope planning processes include all
Q26: The overall project is considered to be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents