The normal activity duration of Activity X is 5 weeks and is budgeted to cost $12,000.The crash time for this activity is 3 weeks and is expected to cost $32,000.The cost slope for Activity X is calculated as ______.
A) (32,000 - 12,000) / (5 - 3)
B) (12,000 - 32,000) / (5 - 3)
C) (32,000 - 12,000) / (3 - 5)
D) (12,000 - 32,000) / (3 - 5)