Consider a programmer who is required to complete four work assignments.Each assignment takes 50 hours to complete.Assume an overhead rate of $1.50 and the cost per hour for the programmer's services to be $35/hour.The direct billing charge will be ______.


A) $10,000
B) $12,000
C) $10,500
D) $11,500

Correct Answer: