PERT Charts Differ from the Critical Path Method in One

Question 98

Multiple Choice
PERT charts differ from the critical path method in one important way. What is it?
A) PERT charts assign one time to finish each task.
B) PERT charts are based on the use of quality principles.
C) PERT charts assign three time estimates for each activity.
D) PERT charts can be used in service organizations.

PERT charts differ from the critical path method in one important way. What is it?


A) PERT charts assign one time to finish each task.
B) PERT charts are based on the use of quality principles.
C) PERT charts assign three time estimates for each activity.
D) PERT charts can be used in service organizations.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents