If prototype testing can be started only after the completion of the prototype,then this is an example of a(n)
A) external dependency.
B) discretionary dependency.
C) replicated dependency.
D) mandatory dependency.
Correct Answer:
Verified
Q54: The shortest time in which an activity
Q55: Which of the following is used to
Q56: Dependencies defined by the project team are
A)discretionary
Q57: The amount of time that an activity
Q58: Basic reasons for creating dependencies of project
Q60: Dependencies involving relationships between the project and
Q61: A method of planning and managing projects
Q62: Which of the following includes activities performed
Q63: Shortening an activity is called
A)float.
B)crash.
C)reduction.
D)smoothing.
Q64: The ratio of rise and run of