Which of the following is a relationship in which the "from" activity cannot start until the "to" activity is started?
A) Start-to-start
B) Finish-to-finish
C) Finish-to-start
D) Start-to-finish
Correct Answer:
Verified
Q48: A(n) _ on a project is a
Q49: Which of the following types of dependencies
Q50: AOA network diagrams use only _ dependencies.
A)start-to-start
B)finish-to-start
Q51: In project time management, the next step
Q52: A network diagramming technique in which boxes
Q52: The critical path is the _ path
Q54: Which of the following is true of
Q55: _ provide(s) a standard format for displaying
Q56: In an AOA network diagram, _ occur
Q57: The amount of time an activity can