You are considering two independent projects both of which have been assigned a discount rate of 12 percent.Project A costs $39,100 and produces cash flows of $15,900 a year for 3 years.Project B costs $22,900 and produces cash flows of $14,000 a year for 2 years.Based on the profitability index,what is your recommendation concerning these projects?
A) Accept both projects
B) Accept Project B because it has the lower PI
C) Accept Project A because it has the lower PI
D) Accept Project A and reject Project B
E) Reject Project A and accept Project B
Correct Answer:
Verified
Q70: A project has an initial cost of
Q71: A new product has start-up costs of
Q72: Project A has an initial cost of
Q73: Assume a project has an initial cost
Q74: A project has an initial cost of
Q75: The Walk-Up Window is considering two mutually
Q76: A project has an initial cash inflow
Q78: A project has an initial cash inflow
Q79: A proposed project has an initial cost
Q80: Project I has an initial cash outflow
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents