Which Methods of Project Analysis Are Most Biased Towards Short-Term

Question 20

Multiple Choice

Which methods of project analysis are most biased towards short-term projects?


A) Net present value and internal rate of return
B) Payback and discounted payback
C) Accounting rate of return and internal rate of return
D) Payback and accounting rate of return
E) Internal rate of return and discounted payback