One Unit of Product a Is Made of Two Units

Question 108

Essay

One unit of product A is made of two units of B and four units of C.B is made of two units of D and three units of E.C is made of three units of D and two units of F.A,C,D,and E have lead times of one week,and B and F have lead times of two weeks.If 100 units of A are required in week 5,develop the material requirements plan specifying when items are to be ordered and received.There are no units of inventory on hand.Hint: Since there are no units of inventory on hand,gross requirements will be equal to net requirements. 100 units of A should be ordered in the fourth week because these units are needed in the fifth week and the lead time is one week. One unit of product A is made of two units of B and four units of C.B is made of two units of D and three units of E.C is made of three units of D and two units of F.A,C,D,and E have lead times of one week,and B and F have lead times of two weeks.If 100 units of A are required in week 5,develop the material requirements plan specifying when items are to be ordered and received.There are no units of inventory on hand.Hint: Since there are no units of inventory on hand,gross requirements will be equal to net requirements. 100 units of A should be ordered in the fourth week because these units are needed in the fifth week and the lead time is one week.
One unit of product A is made of two units of B and four units of C.B is made of two units of D and three units of E.C is made of three units of D and two units of F.A,C,D,and E have lead times of one week,and B and F have lead times of two weeks.If 100 units of A are required in week 5,develop the material requirements plan specifying when items are to be ordered and received.There are no units of inventory on hand.Hint: Since there are no units of inventory on hand,gross requirements will be equal to net requirements. 100 units of A should be ordered in the fourth week because these units are needed in the fifth week and the lead time is one week.
One unit of product A is made of two units of B and four units of C.B is made of two units of D and three units of E.C is made of three units of D and two units of F.A,C,D,and E have lead times of one week,and B and F have lead times of two weeks.If 100 units of A are required in week 5,develop the material requirements plan specifying when items are to be ordered and received.There are no units of inventory on hand.Hint: Since there are no units of inventory on hand,gross requirements will be equal to net requirements. 100 units of A should be ordered in the fourth week because these units are needed in the fifth week and the lead time is one week.
One unit of product A is made of two units of B and four units of C.B is made of two units of D and three units of E.C is made of three units of D and two units of F.A,C,D,and E have lead times of one week,and B and F have lead times of two weeks.If 100 units of A are required in week 5,develop the material requirements plan specifying when items are to be ordered and received.There are no units of inventory on hand.Hint: Since there are no units of inventory on hand,gross requirements will be equal to net requirements. 100 units of A should be ordered in the fourth week because these units are needed in the fifth week and the lead time is one week.
One unit of product A is made of two units of B and four units of C.B is made of two units of D and three units of E.C is made of three units of D and two units of F.A,C,D,and E have lead times of one week,and B and F have lead times of two weeks.If 100 units of A are required in week 5,develop the material requirements plan specifying when items are to be ordered and received.There are no units of inventory on hand.Hint: Since there are no units of inventory on hand,gross requirements will be equal to net requirements. 100 units of A should be ordered in the fourth week because these units are needed in the fifth week and the lead time is one week.
One unit of product A is made of two units of B and four units of C.B is made of two units of D and three units of E.C is made of three units of D and two units of F.A,C,D,and E have lead times of one week,and B and F have lead times of two weeks.If 100 units of A are required in week 5,develop the material requirements plan specifying when items are to be ordered and received.There are no units of inventory on hand.Hint: Since there are no units of inventory on hand,gross requirements will be equal to net requirements. 100 units of A should be ordered in the fourth week because these units are needed in the fifth week and the lead time is one week.

Correct Answer:

verifed

Verified

blured image
100 units of A would require 200 units...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents