A project is comprised of 6 activities that have durations and precedence requirements shown in the table.Which of these activities is not on the critical path?
A) A
B) B
C) C
D) D
Correct Answer:
Verified
Q12: Performance or time targets for each major
Q15: PERT is an acronym meaning:
A)Project Evaluation and
Q17: A forward pass through a network is
Q19: The BEST use of a Gantt chart
Q19: The budget estimates made during the concept
Q21: This Gantt chart can be used to
Q25: What is the latest that activity B
Q26: What is the fastest completion time of
Q27: A hatmaker,fresh off a very successful showing
Q41: The earliest start time of an activity