Question 153

Multiple Choice

One of the events of the critical path for producing a textbook is editing the manuscript. This means that if there is a delay in the editing process, there will be


A) no effect on the overall production process.
B) more resources devoted to those events not on the critical path.
C) no other events taking place until the delay is over.
D) a delay in the completion of the project as a whole.
E) a delay in all the events not on the critical path.