In the Earliest Stages of the Just-In-Time Training Project,which Task

Question 33

Multiple Choice

In the earliest stages of the Just-In-Time Training project,which task is completed first?


A) The project is approved through a formal project selection process.
B) The project manager produces a business case.
C) The project manager holds a kickoff meeting with key team members.
D) The project manager produces a stakeholder analysis.