EV-AC =
A) Cost performance index (CPI)
B) Scheduled performance index (SPI)
C) Cost Variance (CV)
D) Minimum funds needed (MFN)
E) None of these
Correct Answer:
Verified
Q25: Cost Variance (CV) = Earned Value -
Q26: A _ shows how the scope, features
Q27: The metric that provides an estimate of
Q28: The total planned cost of the project
Q29: Budget At Completion (BAC) is _
A) how
Q31: If you hired a consulting firm to
Q32: The budgeted cost of work scheduled for
Q33: Cost Variance (CV) is _
A) how much
Q34: Earned Value tells us _
A) how much
Q35: Expected Time to Completion (ETC) is _
A)
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents