Installing the operating system on a computer before loading any application packages is an example of:
A) Finish-To-Start (FS)
B) Start-To-Start (SS)
C) Finish-To-Finish (FF)
D) Start-To-Finish (SF)
E) none of these
Correct Answer:
Verified