An estimation technique characterized by the allocation of a timeframe for a specified activity.e.g.a team has two weeks to complete a task and at the end of two weeks work on that task ceases.
A) Guesstimating
B) Delphi Technique
C) Time Boxing
D) Top-Down Estimating
E) Bottom-Up Estimating
Correct Answer:
Verified
Q43: _ can be very effective and provide
Q44: A significant event or achievement that provides
Q45: The significant event at the conclusion of
Q46: An estimation technique characterized by the recruitment
Q47: In the WBS context, a crux is
Q49: An estimation technique characterized by picking numbers
Q50: _ is the most common, real-world method
Q51: Which of the following processes of Scope
Q52: The Work Breakdown Structure is subdivided into
Q53: Continuously agreeing to project changes is an
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents